In March 2026 we replaced a leaking 553 sq ft garage roof section in Stockton for a signed $9,129.92, 25 days from the City permit to its final inspection. Stockton requires a City permit for every re-roof, even a new layer over the old one, and we always apply for the permit ourselves.
A leaking garage roof, replaced as one new roof section.
The roof leaked in several places over the garage, so the homeowner chose to replace that whole roof section and keep the rest of the house roof. It is one of two re-roofs we have finished in Stockton.
01
What we found
Leaks in several places over the garage. When the old shingles came off, the underlayment had failed and the wood under it was water-damaged in several spots, so patching one area would have left the rest failing.
Leaks in several places
Worn shingles and underlayment
Water-damaged wood under them
02
What the signed $9,129.92 covered
Tear-off of the one old shingle layer over about 553 sq ft and the haul-off; a sheathing repair allowance; synthetic underlayment; self-adhered membrane at the eaves and valleys; metal drip edge; flashing; a ridge vent; architectural asphalt shingles; the cleanup; and the permit and inspection allowance. See the full job story with the photos.
How the Stockton garage re-roof went, step by step.
01
Permit, then tear-off
With the City re-roof permit issued on March 2, the one old layer of asphalt shingles came off the whole garage section and was hauled away.
02
Damaged wood replaced first
The open deck showed the water-damaged wood. Stockton has all damaged wood replaced before its in-progress inspection, so the new sheathing went in first.
03
Layers that keep water out
Synthetic underlayment went over the deck, self-adhered membrane at the eaves and valleys, and metal drip edge and flashing along the edges.
04
Shingles, cleanup and final
Architectural asphalt shingles and a ridge vent went on, the site was cleaned, and the City passed the final inspection on March 27, 2026.
Job photos
From the old roof to the new layers, on the same Stockton garage.
Every photo here is from this job. The project page has the whole story.
They made the replacement for the roof over the garage very simple. No guess work or trying to sell you more. Very good work and at better prices than some other roofers I called. Cleaned up everything when job was done and it looks great.
Does a roof replacement in Stockton need a City permit?
Yes, every re-roof does. The City's Residential Reroof Requirements (BLDG-0019) say: "A permit is required for all reroof projects including adding an additional layer of roof covering to an existing roof."
Item
What Stockton says
Source
Every re-roof
A permit for all re-roof projects, a new layer over the old roof included.
When more than half of a home's roof is replaced. BLDG-0019 applies the rule "When more than 50% of the exterior surface of a residential roof is being replaced".
Item
What Stockton says
Source
Steep roofs (2:12 or more)
Climate Zone 12: aged solar reflectance at least 0.20 and thermal emittance at least 0.75.
Half of Stockton homes (50.7%) were built before 1980. On an older house, ask how many layers the roof already has: with two, the City requires a full tear-off.
Item
What it means
Source
Stockton homes
50.7% built before 1980; median year built 1980; 66.8% single-family detached.
In 2024 we replaced a full 1,145 sq ft hip roof in Stockton, with the solar panels taken down and put back as part of the job: the full roof with solar.
Yes. The City of Stockton says: "A permit is required for all reroof projects including adding an additional layer of roof covering to an existing roof." We always apply for the permit ourselves and plan the work around the City inspections.
Yes, when more than half of a home's roof is replaced. For steep roofs in Climate Zone 12 the product needs an aged solar reflectance of at least 0.20 and a thermal emittance of at least 0.75, rated by the Cool Roof Rating Council. The City also accepts R-38 roof or ceiling insulation, a radiant barrier, no ducts in the attic, or R-2 continuous insulation instead.
Only if the roof has one layer now. The City allows at most two layers, and "if the existing roof already has two layers, a complete tear off is required." An overlay still needs the City permit. On our garage job the one old layer came off down to the deck.
A signed $9,129.92 for about 553 sq ft: the tear-off, a sheathing allowance, synthetic underlayment, self-adhered membrane at the eaves and valleys, metal drip edge, flashing, a ridge vent, architectural shingles, the cleanup, and the permit and inspection allowance. The final invoice was the same, with no change orders. This was one garage roof section; a whole roof is priced after we measure it.
Our garage job took 25 days from the City permit on March 2 to the final inspection on March 27, 2026, with the in-progress inspection the City requires in between. You get approximate start and finish dates in your contract before you sign.
Stockton roof replacement
Book a free roof inspection in Stockton.
Send photos of the roof any day from 9 AM to 5 PM. After the free inspection you get a written, signed price, and any extra work is written up and priced before it is done. The down payment is never more than $1,000 or 10%, whichever is less. Veterans and seniors get 10% off. For siding, kitchens and bathrooms, see our Stockton page.