Roof replacement in Stockton, CA: two re-roofs, City rules

In March 2026 we replaced a leaking 553 sq ft garage roof section in Stockton for a signed $9,129.92, 25 days from the City permit to its final inspection. Stockton requires a City permit for every re-roof, even a new layer over the old one, and we always apply for the permit ourselves.

Our Stockton job · March 2026

A leaking garage roof, replaced as one new roof section.

The roof leaked in several places over the garage, so the homeowner chose to replace that whole roof section and keep the rest of the house roof. It is one of two re-roofs we have finished in Stockton.

01

What we found

Leaks in several places over the garage. When the old shingles came off, the underlayment had failed and the wood under it was water-damaged in several spots, so patching one area would have left the rest failing.

  • Leaks in several places
  • Worn shingles and underlayment
  • Water-damaged wood under them
02

What the signed $9,129.92 covered

Tear-off of the one old shingle layer over about 553 sq ft and the haul-off; a sheathing repair allowance; synthetic underlayment; self-adhered membrane at the eaves and valleys; metal drip edge; flashing; a ridge vent; architectural asphalt shingles; the cleanup; and the permit and inspection allowance. See the full job story with the photos.

  • Signed price: $9,129.92, no change orders
  • City permit to final: March 2 to 27, 2026
  • Project lead: Evon Celik
Old stained roof boards next to new sheathing panels on the Stockton garage roof
Old roof boards next to new sheathing on the Stockton garage roof, March 2026 · View the documented project

On the roof · March 2026

How the Stockton garage re-roof went, step by step.

Permit, then tear-off

With the City re-roof permit issued on March 2, the one old layer of asphalt shingles came off the whole garage section and was hauled away.

Damaged wood replaced first

The open deck showed the water-damaged wood. Stockton has all damaged wood replaced before its in-progress inspection, so the new sheathing went in first.

Layers that keep water out

Synthetic underlayment went over the deck, self-adhered membrane at the eaves and valleys, and metal drip edge and flashing along the edges.

Shingles, cleanup and final

Architectural asphalt shingles and a ridge vent went on, the site was cleaned, and the City passed the final inspection on March 27, 2026.

From our Google reviews

The homeowner's Google review of this job

The homeowner wrote this review on Google after our Stockton garage re-roof. It is shown word for word.

5.0 from 131 reviews on Google · Read all reviews on Google

  1. They made the replacement for the roof over the garage very simple. No guess work or trying to sell you more. Very good work and at better prices than some other roofers I called. Cleaned up everything when job was done and it looks great.

    Darin SelbyGoogle review · Read on Google

City of Stockton rules

Does a roof replacement in Stockton need a City permit?

Yes, every re-roof does. The City's Residential Reroof Requirements (BLDG-0019) say: "A permit is required for all reroof projects including adding an additional layer of roof covering to an existing roof."

Item
What Stockton says
Source
Every re-roof
A permit for all re-roof projects, a new layer over the old roof included.
Layers
At most two layers of roofing; "if the existing roof already has two layers, a complete tear off is required."
In-progress inspection
"In-progress inspection (015) is required." All damaged wood is replaced before it.
Sheathing
Exterior grade, at least 7/16 inch for plywood and 11/32 inch for OSB.
Edges and flashing
Drip edge at the eaves and gables of shingle roofs; rusted or damaged flashing and metal edging replaced with new.
Fire class
Roof covering at least Class C, the minimum for a typical wood-frame house.
Tile instead of shingles
A heavier roof may need an engineer's check that the roof structure can carry it.
On the job site
The signed permit card and the inspection record.

Cool roof rule

When does a Stockton re-roof need a cool roof?

When more than half of a home's roof is replaced. BLDG-0019 applies the rule "When more than 50% of the exterior surface of a residential roof is being replaced".

Item
What Stockton says
Source
Steep roofs (2:12 or more)
Climate Zone 12: aged solar reflectance at least 0.20 and thermal emittance at least 0.75.
Rated and labeled
The product is rated by the Cool Roof Rating Council (CRRC) and labeled by the maker; the packages stay on site for the inspector.
Instead of a cool roof
For steep roofs: R-38 roof or ceiling insulation, a radiant barrier, no ducts in the attic, or R-2 continuous insulation above or below the deck.
Exempt
Non-habitable structures such as detached garages, and roof area covered by building-integrated solar.

Stockton homes

Replace one roof section or the whole roof?

Half of Stockton homes (50.7%) were built before 1980. On an older house, ask how many layers the roof already has: with two, the City requires a full tear-off.

Item
What it means
Source
Stockton homes
50.7% built before 1980; median year built 1980; 66.8% single-family detached.
One section
Our garage job replaced the one roof section where the leaks were and kept the rest of the house roof. See the garage roof job.
The whole roof
In 2024 we replaced a full 1,145 sq ft hip roof in Stockton, with the solar panels taken down and put back as part of the job: the full roof with solar.
See it first
See roof repair and replacement. We can show the new roof on your house in 3D for free before you sign: how the free design works.

Stockton roof replacement questions

Questions before a Stockton roof replacement.

Water-damaged wood under the edge of the Stockton garage roof, seen from below

Stockton roof replacement

Book a free roof inspection in Stockton.

Send photos of the roof any day from 9 AM to 5 PM. After the free inspection you get a written, signed price, and any extra work is written up and priced before it is done. The down payment is never more than $1,000 or 10%, whichever is less. Veterans and seniors get 10% off. For siding, kitchens and bathrooms, see our Stockton page.

Crew tearing the old asphalt shingles off the Stockton garage roof section
This website uses cookies to improve your web experience.
Explore
Drag