Completed project / Sacramento, California

Commercial Sewer Line Replacement in Sacramento

A restaurant’s sewer line below the slab, replaced in two phases, with the floors and walls restored afterwards.

US Construction Remodeling Corp. replaced about 160 linear feet of drain-waste-vent piping below the slab of a Sacramento restaurant, coordinated the grease interceptor and fixture connections, restored the concrete, and then repaired the flooring and walls in the affected areas.

Restaurant work area in Sacramento after the sewer line replacement
A restaurant work area we opened and restored.
Location
Sacramento, California
Property
Operating restaurant
New piping
About 160 linear ft
Review
City-reviewed drawings, field inspections

The challenge

Reach the sewer line, then rebuild what was in the way.

The restaurant’s drain system ran below the slab. Reaching it meant demolition, excavation, new piping, fixture connections, inspections, backfill and concrete work, and then repairs to the finishes on top.

So the work was split in two: a plumbing and excavation phase, then restoration of the restaurant areas the utility work had opened.

The scope

What the two phases included.

  1. 01

    Plumbing, excavation and slab

    • Site protection, sawcutting, demolition and removal
    • Trench excavation, crushed-rock bedding, backfill and compaction
    • New ABS drain-waste-vent piping, fittings, cleanouts and floor drains
    • Grease interceptor, mop sink, toilet, trap and vent connections
    • Reinforcement, concrete patching, line service after the work, and cleanup
  2. 02

    Restaurant interior restoration

    • New flooring in the affected restroom and restaurant areas
    • Wall repairs where the plumbing work needed access
    • Coordination across the sales, food preparation, kitchen and restroom areas
    • Finish work scheduled after the underground and concrete work
    • Final cleanup and a completion review of the work areas

Photos from the job

From the trench to the restored room.

Photos taken by our team during the work.

Open trench with crushed-rock bedding along the new sewer line
The trench with crushed-rock bedding.
New drain line laid in the trench below the restaurant slab
The new line in the trench, before backfill.
Worker connecting new ABS drain piping where the restaurant floor was opened
New ABS piping connected where the floor was opened.

How the work moved

From access to restoration, in order.

  1. 01

    Protect and open

    Mark the work zone, protect the areas around it, sawcut the slab and expose the pipe route.

  2. 02

    Replace and connect

    Install the new piping and connect the fixtures, vents and grease interceptor.

  3. 03

    Inspect and close

    Pass the field inspections before backfill, compaction, reinforcement and concrete cover the work.

  4. 04

    Restore the rooms

    Repair the flooring and walls once the underground work and slab are done.

Drawings and inspections

Reviewed drawings, inspected work.

City-reviewed drawings were issued for this Sacramento project, and the plumbing and mechanical work was inspected in the field before it was covered.

Another commercial property’s requirements depend on its address, use, existing conditions and scope. Read our permit and inspection guide

Commercial sewer questions

What people ask about a project like this.

Was this a small repair or a full commercial sewer project?

A full project: the sewer line ran below the slab, so the work took slab access, new drain-waste-vent piping, fixture connections, concrete restoration and then repairs to the floors and walls.

What was in the plumbing and excavation phase?

Site protection, sawcutting and demolition, trench excavation, bedding, about 160 linear feet of new drain-waste-vent piping, cleanouts, floor drains, grease interceptor connections, backfill, compaction and concrete patching.

Why was the interior restoration a second phase?

The underground plumbing and the slab had to be finished first. Floors and walls were repaired after that, so new finishes did not go in before the utility work was done.

Were city-reviewed drawings part of the project?

Yes. City-reviewed drawings were issued, and the plumbing and mechanical work was inspected in the field. Another property’s requirements depend on its address, use and scope.

Can a commercial sewer replacement need concrete and finish repairs?

Yes. Piping under a slab means sawcutting, excavation, backfill and concrete work, and the floors, walls and fixtures in the way need to be restored afterwards.

Commercial plumbing

Planning sewer or below-slab plumbing work?

Send the property address, what you are seeing, when the business can close an area, and any drawings you already have.