Free 3D design for any room in your home, siding or roof, before you sign10% off for veterans and seniorsFree 3D design10% off for veterans and seniors

Skip links

Commercial build-outs · Sacramento County

Sacramento County Health Plan Review for Bar and Cafe Build-Outs

The health plans are approved before the building permit is issued. Plan for that order and the build-out keeps moving.

What the County Environmental Management Department (EMD) reviews, what it costs in fiscal year 2026-27, how long it takes, and the bar and cafe details that most often come back with corrections.

Front counter area of a Sacramento restaurant during our sewer line and restoration project
An operating Sacramento restaurant. The front counter during our sewer line and restoration project.

The order

In what order do the approvals happen?

Health first, then the building permit, then the final health inspection.

  1. Check the space before the lease

    A former cafe is not automatically ready for a bar. If the space was not a restaurant, the City says it may need a grease interceptor, a hood with make-up air, gas or electrical upgrades, exits and an accessible path of travel.

  2. Freeze the equipment list

    Pick the equipment and collect the spec sheets before the plans go in. A change after submittal means revised plans and another review.

  3. Submit to the County first

    The City of Sacramento asks for proof of the County submittal with the building application, and the approved health plans before it issues the permit.

  4. County review

    State law gives the County 20 working days to approve or reject a complete plan, or the plan is deemed approved. For a restaurant tenant improvement, a resubmittal is reviewed within 10 business days since 2026.

  5. Build and inspect

    The building permit is issued, the work is built and the City inspects it.

  6. Final health inspection

    Call the County at least 2 days ahead. All equipment is in place and working, the water heater is on, the place is clean and the hood balance test is done if there is a hood. You may not open before the final approval and the health permit.

2026-27 fees

How much does the County plan review cost?

The County fee schedule in effect from July 1, 2026 to June 30, 2027.

Sacramento County EMD fees, fiscal year 2026-27
FeeIncludes
New construction under 2,000 sq ft, or a remodel over 50%$2,5613 resubmittals and 2 inspections
New construction 2,000 to 6,000 sq ft$2,940
Major remodel, 25% to 50%$1,4692 resubmittals and 1 inspection
Minor remodel under 25%, with an inspection$981
One piece of equipment, like for like$223
Extra inspection$480
Annual health permit: bar$918Billed after permitting
Annual health permit: restaurant with bar$1,962Billed after permitting

The plan set

What goes into the plans for the County?

From the County application for fiscal year 2026-27.

Drawings

Drawn to scale, at least 1/4 inch per foot, on sheets at least 24 by 36 inches when paper is used. One set at first submittal, three identical sets for the final approval.

Equipment

An equipment floor plan with numbered spec sheets. Food equipment must be certified for sanitation under an accredited program.

Plumbing

Every floor sink and drain labeled, with the water heater size and recovery rate.

Light, air and finishes

A lighting plan, a ventilation plan, hood drawings with make-up air, and a finish schedule for floors, walls and ceilings.

Storage and menu

At least 144 sq ft of storage for a restaurant and 72 sq ft for a small facility such as a bar, plus the menu.

Time limit

The application and its approval expire one year after the date submitted.

Bar and cafe rules

Which rules do bars and cafes meet most often?

From the California Retail Food Code in effect in January 2026 and the County guidance.

Hand sinks

Separate hand sinks in the prep and warewashing areas, with warm water (section 113953).

Warewashing

A sink with at least three compartments and two drainboards (section 114099). The County confirms the setup for your menu.

Indirect drains

Ice machines, ice bins and prep and warewashing sinks drain through an air gap into a floor sink (sections 114193 and 114269). The County asks for espresso, soda and beer dispensers to drain to a floor sink nearby.

Floors and walls

Floors smooth and easy to clean, with a cove base at least 4 inches high (section 114268). Walls in a bar where drinks are served directly to customers have more leeway, except next to bar sinks and prep areas (section 114271).

Light

At least 10 foot-candles where drinks are prepared and 20 in warewashing areas and restrooms (section 114252).

Mop sink and restrooms

A janitorial sink (section 114279). Customers must not walk through prep, storage or warewashing areas to reach a restroom (section 114276).

City permits

What else does the City of Sacramento ask for?

Other cities in the county have their own building departments; the County health review is the same everywhere.

Order of approvals

Planning approval comes before the building application, and the approved health plans come before the building permit.

Sewer fee receipt

When the new use increases sewer flow, such as an office becoming a restaurant, the sewer fee receipt is needed before the permit is issued.

Bars

For on-site drinking, a conditional use permit is required for bars, not for restaurants.

Alcohol license

The state license needs a premises diagram (form ABC-257). Keep it the same as the permitted floor plan.

City review time

For alterations under $400,000, the City projects 15 working days for the first review and 10 for each of the next two.

Our restaurant work

What did a restaurant project of ours involve?

An operating Sacramento restaurant, in two phases.

Below the slab

About 160 feet of new drain-waste-vent piping under the floor, with cleanouts, floor drains and the grease interceptor connections.

Reviewed and inspected

City-reviewed drawings, and the plumbing and mechanical work inspected before it was covered.

Restored afterwards

The concrete, then the floors and walls in the restroom and restaurant areas.

Trench with new drain piping and gravel bedding under a Sacramento restaurant floor
The trench with new piping and gravel bedding.
Drain piping replaced along the kitchen wall of a Sacramento restaurant
New drain piping along the kitchen wall.

See the full restaurant project or our restaurant build-out service.

About the author

Who wrote this guide?

Our Chief Designer wrote this guide.

Written by Emin

Chief Designer

Emin is the Chief Designer at US Construction Remodeling Corp. Emin leads client design meetings, measured layouts and 3D visualization in Revit, 3ds Max and Unreal Engine, and uses AI tools to speed up design and project planning.

Planning tools

Which tools help plan a build-out?

Size a sewer or drain trench with the trench calculator, or count paint for the dining room with the paint calculator.

Plan review questions

What else do people ask about the County health review?

Short answers from the County and state pages.

Do I need health department approval before building out a cafe in Sacramento County?

Yes. Plans for a new food facility, a remodel, added equipment or a change in menu or service go to the County Environmental Management Department before construction starts. The County covers every city in the county.

How long does the County plan review take?

State law gives the County 20 working days to approve or reject a complete plan. Since January 1, 2026, a resubmittal for a restaurant tenant improvement is reviewed within 10 business days.

How much is the plan check fee?

For fiscal year 2026-27: $2,561 for new construction under 2,000 sq ft or a remodel of more than half the facility, $1,469 for a major remodel and $981 for a minor remodel with an inspection. The annual health permit is billed separately.

Do I need plan review to take over an existing cafe without changes?

Usually not. The new owner applies for a health permit before taking over. The County may ask for a $480 facility evaluation if the place was closed and had no routine inspection in the last 6 months.

Does a bar need a three-compartment sink?

State code calls for a warewashing sink with at least three compartments and two drainboards, plus separate hand sinks. The County confirms what your menu and equipment need during plan review.

Is a former cafe ready for a bar?

Not automatically. In the City of Sacramento a bar for on-site drinking needs a conditional use permit, the state license needs a premises diagram, and the health plans must show the bar equipment and drains.

Bar and cafe build-outs

Planning a bar or cafe?

Send the address, the floor plan you have and what you will serve. Call or fill out the form, and we come out to look at the space and take measurements.

This website uses cookies to improve your web experience.
Explore
Drag