Who Draws Restaurant Plans and Gets the Permits in Sacramento?

We prepare the permit drawings and apply for the City and County permits ourselves; where the law calls for a licensed design professional’s stamp, we bring one in under our contract. Sacramento County has 20 working days to review the health plans, and the City lists 15 working days for a first building review of an alteration under $400,000.

Below: the order of approvals, who may draw what, review times, sample fees, and how US Construction Remodeling can help.

Plumbing drawing with domestic water, a backflow assembly, a water heater and restroom fixtures
Plumbing drawing with domestic water, a backflow assembly, a water heater and restroom fixtures.

Drawings

We prepare them. A licensed design professional stamps the restaurant plans, under our contract.

Permits

We apply for the City and County permits ourselves and answer the review comments.

Time

County health review: 20 working days. City building review: 15 working days for a first review under $400,000.

The order

In what order do the approvals happen?

For a restaurant inside the City of Sacramento. The building application needs both the County submittal and Planning approval, which can run side by side.

  1. Drawing of an empty restaurant space with markers at a floor drain, a gas meter and a hood route

    Look at the space

    Before the lease we look at the drains, the gas, the electrical service, the restrooms and the hood route.

  2. Drawing of a menu card and an equipment list beside a range, a fryer and a sink

    Settle the menu and equipment

    The County reviews the kitchen from the equipment list, so it comes first. A change after submittal means revised plans.

  3. Drawing of a rolled set of kitchen plans going into a folder in front of a county office

    County health submittal

    The plans go to Sacramento County’s Environmental Management Department. The City asks for proof of that submittal with the building application.

  4. Drawing of a city map of a shopping street with one restaurant highlighted by a green check mark and a small city hall at the end

    City Planning

    Planning approval comes before the building application.

  5. Drawing of a building permit card with a check mark beside a sewer fee receipt and rolled restaurant kitchen plans

    Building permit

    The approved health plans, and the sewer fee receipt when the use sends more to the sewer, come before the City issues the permit.

  6. Drawing of new pipes and wires in an open wall with a checked clipboard leaning against it

    Build and inspect

    City inspectors see the work before it is covered.

  7. Drawing of a restaurant entrance with a green check-mark tag on the door and two framed papers on the wall inside

    Open

    The City’s final inspection, a new certificate of occupancy when the use changed, and the County’s final inspection and health permit come before you serve the first customer. Read change of use and certificate of occupancy.

The drawings

Who is allowed to draw restaurant plans?

The City of Sacramento’s form CDD-0236, revised January 1, 2026, sets the rule.

A licensed design professional

Building plans are prepared and signed by a licensed design professional, unless the work fits the City’s narrow exemption.

The narrow exemption

The City’s exemption covers only simple office or store interiors with one exit and no change to structure or fire safety, so restaurant plans usually carry a stamp.

Every sheet stamped

The City’s submittal checklist asks for the signed stamp on the cover sheet and on every sheet.

Our part

We prepare the permit drawings and run the design team, so the plans, the equipment list and the County set describe the same kitchen.

Lighting plan with fixtures, circuits and emergency lighting
A lighting plan with the fixtures, the circuits and the emergency lighting.

How long

How long do the reviews take?

Published review times, for complete submittals.

County health review

State law gives Sacramento County 20 working days to approve or reject complete plans.

City building review

The City lists 15 working days for the first review of a commercial alteration under $400,000, then 10 for each of the next two.

Small Project Rapid Review

It covers office and store interiors of 3,000 sq ft or less in 1-3 business days. It leaves out first tenant improvements, changes of occupancy, and County health projects sent without the County receipt.

Unincorporated county

Outside city limits, Sacramento County takes about 1-3 days to log the plans, then 14-21 working days to review them.

Roseville

Roseville lists about 3 weeks for a first review. A simple tenant improvement may be reviewed within one business day.

Fire

Metro Fire, which covers most of the unincorporated county, takes about 20 business days. The kitchen hood’s fire suppression system is its own fire submittal.

What it costs

What do the City permit fees come to?

The City of Sacramento sets building fees from the job’s value: its valuation table or the contract price, whichever is higher. Sample rows from form CDD-0216, revised July 12, 2026.

A $24,999 job

Building permit $475, plan review $373.

A $49,999 job

Building permit $704, plan review $561.

A $99,999 job

Building permit $1,078, plan review $866.

Added to each

A 10% technology fee on the permit and plan review, a General Plan fee of $2.60 per $1,000 of value, and smaller state fees.

Fire

City fire plan review is $260 an hour, and the fire inspection for a remodel is 8 cents a square foot, at least $294.

Sewer fee

When the new use sends more to the sewer, as when an office becomes a restaurant, the Regional Sanitation fee is due before the permit.

County health

The County plan check fee for 2026-27 follows the size of the remodel. Our health plan review guide lists it.

How we can help

How can US Construction Remodeling help with the plans and permits?

From the first look at the space to the final inspection, US Construction Remodeling can handle each step with you.

Before you sign

We walk the space with you and list the reviews it will need, so there are no surprises after the lease.

Drawings

We prepare the permit drawings, and where the plans need a licensed design professional’s stamp, we bring one in under our contract.

Permits and comments

We apply for the City and County permits ourselves and answer the review comments sheet by sheet.

Build and inspections

We build the work and call the inspections, so nothing is covered before the inspector has seen it.

Have a space in mind? Send the address and the menu, and we will tell you which reviews it needs.

Get my free estimateRestaurant build-outs

About the author

Who wrote this guide?

Our Chief Designer wrote this guide.

Written by Emin

Chief Designer

Emin is the Chief Designer at US Construction Remodeling Corp. Emin leads client design meetings, measured layouts and 3D visualization in Revit, 3ds Max and Unreal Engine, and uses AI tools to speed up design and project planning.

Sources

Where can you check these facts?

The City, County and fire district pages behind these steps.

Practical questions

What else do restaurant owners ask about plans and permits?

Short answers from the City and the County.

Who draws the plans for a restaurant build-out?

We prepare the permit drawings. Restaurant plans in the City of Sacramento usually carry a licensed design professional’s stamp, and we bring one in under our contract.

Who applies for the permits?

We always apply for the permit ourselves, with the City and the County, and we answer the review comments.

Do I need County health approval before the City permit?

Yes. The City asks for proof of the County submittal with the building application, and the approved health plans before it issues the permit.

How long does permitting take for a Sacramento restaurant?

The County has 20 working days for complete health plans, and the City lists 15 working days for a first building review of an alteration under $400,000. Each resubmittal adds a review.

What does a City building permit cost?

For a $49,999 job the City lists a $704 permit and $561 plan review, plus a 10% technology fee and smaller state fees.

Does a kitchen hood need its own fire review?

Yes. The hood’s fire suppression system is a separate fire submittal with its own fee. Inside the City, fire plan review is $260 an hour; in Metro Fire’s area it is $1,327 per system.

Plan your project

Opening a restaurant in Sacramento?

Send the address, the menu and the equipment list. We look at the space for free and send a written price that names the drawings, the permits and the build.